75. What problem does the speaker mention?
(A) A document has been lost.
(B) A permit has not been approved yet.
(C) The client cancelled the project.
(D) The construction materials are defective.

答案:登入後查看
統計: A(1), B(44), C(0), D(9), E(0) #3822845

詳解 (共 1 筆)

#7344429
Hello Mr. Tanaka, this is Sarah Jenkins from Jenkins Architecture. I'm calling regarding the blueprints for your new office complex on 4th St. Unfortunately, the City Planning Council has requested a modification to the drainage system design before they will issue the final building permit. This means.You will have to delay the start of construction by at least two weeks. I have already drafted A revised plan and I would like to review it with you. Could you please let me know if you are available for a video call this Thursday 