16、 在物料需求規劃(MRP,Material Requirement Planning)中,其最頂層之輸入需求為?
(A) Final assembly scheduling (FAS)
(B) Capacity requirements planning (CRP)
(C) Master production schedule (MPS)
(D) Operations sequencing (OS)
(E) Production activity control(PAC)
詳解 (共 1 筆)
未解鎖
MRP為輸入MPS、BOM、ISR,輸出...