17. Consider five processes as follows. They arrived in the order of P1, P2, P3, P4, and P5 at time 0. What is the total turnaround time of all processes by using the shortest-job-first (SJF) scheduling algorithm?

(A) 25
(B) 30
(C) 35
(D) 40
(E) 45