25. The team worked ______ to meet the tight deadline for the project.
(A) against the clock
(B) at a casual pace
(C) with a laid-back approach
(D) out of hand
答案:登入後查看
統計: A(186), B(12), C(33), D(21), E(0) #3227345
統計: A(186), B(12), C(33), D(21), E(0) #3227345