68. A Gantt chart is a type of bar chart that illustrates a project schedule. Which one of the
following statements about the Gantt chart is NOT true?
(A)Gantt charts illustrate the start and finish dates of the terminal elements and
summary elements of a project
(B)Gantt charts use the work breakdown structure, which splits an element into multiple
small components
(C)Unfortunately, Gantt charts cannot show the dependency of each component. So
sometimes we need to use other tools, like Mind Map, to record the dependency
(D)Gantt charts are the preferred tool for project managers working in the waterfall
model