5. CIP(Coordinate Installation Program)「施工界面協調計畫」,係透過
(A)爭議調解
(B)訴訟
(C)局部工程暫時移交供後續施工移交單及界面協調會
(D)仲裁 解決界面問題
答案:登入後查看
統計: A(78), B(7), C(722), D(36), E(0) #878145