43、 專案計畫中之臨界路徑(Critical path)為:
(A) The shortest path in the project network (B) The activity on this path has zero slack
(C) Any delays along the path will delay the completion time of the project
(D) The longest path in the project network (E) The activity on this path has the largest slack