12 甲公司標準工資率為每小時$300,實際人工小時數為5,000 小時。若發生不利的效率差異$60,000,有利的工資率差異$20,000,則實際人工成本為何?
(A)$1,460,000
(B)$1,480,000
(C)$1,520,000
(D)$1,540,000
答案:登入後查看
統計: A(0), B(27), C(2), D(2), E(0) #407260
統計: A(0), B(27), C(2), D(2), E(0) #407260
詳解 (共 1 筆)
#787408
AP*AQ=$296*5,000=$1,480,000(實際人工成本)
SP*AQ=$300*5,000=$1,500,000(外加數)
SP*AQ=$300*5,000=$1,500,000(外加數)
SP*SQ=$300*4,800=$1,440,000(標準人工成本)