4. (10%)
(b) Are there any other construction project delivery method? What is its advantage?
相關申論題
1. (12%) Name and briefly describe each of the two basic types of competitively bid construction contracts. What are their pros and cons? List an example work suitable for cach of competitively bid construction contracts.
#420986
2. (6%) Name two types of negotiated contracts and describe the method of payment and incentive concept.
#420987
3. (9%) Describe three different stakeholders involved in a construction project. Describe their roies and responsibility.
#420988
(a) Compare Design-Build and Design-Bid-Build; what are their pros and cons? (3%)
#420989
(a) A common and effective project management technique is to assign more people to the team if a project gets bchind schedule.
#420991
(b) One key to successful project management is to commit to a fixed budget and schedule as carly as possible and then stick to it.
#420992
(c) The construction drawings of a building project are drawings that the architect uses to cxpiain the design to the owner.
#420993
(d) BIM is the most recently developed project delivery method.
#420994
6. (15%) For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the tablc.
#420995
7. (5%) What is the primary concern of material management on a project?
#420996
相關試卷
110年 - 110 國立宜蘭大學_碩士班招生考試_土木工程學系丙組:營建管理#102114
110年 · #102114
110年 - 110 國立臺灣科技大學_碩士班招生試題_營建工程系(甲組):營建管理#101964
110年 · #101964
110年 - 110 國立臺灣大學_碩士班招生考試_土木工程研究所營建管理組:營建管理#100572
110年 · #100572
109年 - 109 國立宜蘭大學_碩士班招生考試_土木工程學系碩士班丙組:營建管理#103062
109年 · #103062
103年 - 103 淡江大學 轉學考 營建管理#53037
103年 · #53037