38 下列何種計劃工具,主要是針對特別需要關注與監督的工作項目,以網路圖規劃整個計畫?
(A)計畫評核術(Program Evaluation and Review Technique, PERT)
(B)要徑法(Critical Path Method, CPM)
(C)甘特圖(Gantt Chart)
(D)主生產計劃(Master Production Schedule, MPS)
統計: A(3968), B(929), C(388), D(188), E(0) #1669693
詳解 (共 10 筆)
計畫評核術(PERT)
1.將專案計畫之執行先後流程或步驟以網路圖表示。
2.每一步驟之過程需估算出樂觀(t0)、悲觀(tp)及最可能時間(tm),再據以計算其預期時間(te)(三時估計法),te=(t0+4tm+tp)/6。
3.在網路圖中須找出累積工時最長之途徑,並加強管理此一途徑。
4.此項技術兼具規劃與控制功能。
要徑法(CPM)
1.與PERT雷同,但使用單時估計法(可能時間計算)。
2.重視趕工成本估算。
要徑法(Critical Path Method, CPM) 要徑法是條路 這樣就不會和PERT搞混

(1)
PERT is a project management technique, whereby planning, scheduling, organising, coordinating and controlling uncertain activities are done.
CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities take place.
(2)
PERT is a technique of planning and control of time.
Unlike CPM, which is a method to control costs and time.
參考資料:Difference Between PERT and CPM
https://keydifferences.com/difference-between-pert-and-cpm.html
PERT 網路是一種類似流程圖的箭線圖。它描繪出專案包含的各種
活動的先後次序,標明每項活動的時間或相關的成本。對於 PERT 網路,專案管理者必須考慮要做哪些工作,確定時間之間的依賴關係,辨認出潛在的可能出問題的環節,借助 PERT 還可以方便地比較不同行動方案在進度和成本方面的效果。
簡單地說,PERT 是利用網路分析制定計劃以及對計畫予以評價的技術。它能協調整個計畫的各道工序,合理安排人力、物力、時間、資金,加速計畫的完成。在現代計畫的編制和分析手段上,PERT 被廣泛的使用,是現代化管理的重要手段和方法。