535 欲將專案劃成網路,而需先行建立活動之間的以下何者?
(A)先行關係
(B)利害關係
(C)強制依存關係
(D)外部依存關係
答案:登入後查看
統計: A(80), B(13), C(9), D(11), E(0) #1612311