662 下列哪一項是風險管理計畫的內容?
(A)員工的士氣
(B)專案計畫書的完整性
(C)編列預算
(D)專案財務結算
答案:登入後查看
統計: A(1), B(45), C(38), D(6), E(0) #1612438
統計: A(1), B(45), C(38), D(6), E(0) #1612438
詳解 (共 1 筆)
#5968153
風險管理計畫書:
.方法論 (Methodology)
.角色與責任(Roles and Responsibilities)
.編列預算(Budgeting)
.時機(Timing)
.風險類別(Risk categories)
.風險機率及衝擊定義(Definitions of risk probability and impact)
.機率及衝擊矩陣 (Probability and impact matrix)
.經修正的利害關係人容忍度(Revised stakeholders’tolerances)
.報告格式(Reporting formats)
.追蹤(Tracking)
資料來源:Ethan's information radiators