94.計劃評核術(PERT)的T是指
(A)計劃
(B)評估
(C)覆核
(D)技術----P.91
答案:登入後查看
統計: A(15), B(64), C(112), D(988), E(2) #29881
統計: A(15), B(64), C(112), D(988), E(2) #29881
詳解 (共 1 筆)
#39648
Program Evaluation Review Technic